Earned Value Calculator

// project performance instrument

Earned value calculator

Enter your project's baseline and progress to see PV, EV, AC, cost and schedule performance indices, and a forecast at completion — standard EVM.

Project baseline and progress

Value comparison

Planned value (PV)$0
Earned value (EV)$0
Actual cost (AC)$0
Cost performance (CPI)
0.00
—
Schedule performance (SPI)
0.00
—

Forecast at completion

Cost variance (CV)
$0
Schedule variance (SV)
$0
Estimate at completion (EAC)
$0
Estimate to complete (ETC)
$0
Variance at completion (VAC)
$0
To-complete index (TCPI)
0.00

EAC here uses the common BAC ÷ CPI formula, which assumes current cost performance continues for the remainder of the work. Other EAC formulas exist for different risk assumptions — this is a starting estimate, not a contractual forecast.