Machine Productivity Calculator
Calculate Overall Equipment Effectiveness (OEE) for a production run.
Planned Production Time
min
Scheduled run time for the shift, e.g. 480 min for an 8-hour shift
Downtime
min
Stoppages: breakdowns, changeovers, material shortages, etc.
Ideal Cycle Time
sec/unit
Fastest possible time to produce one unit, per the machine's spec
Total Units Produced
All units produced during the run time, good and defective
Good Units
Units that passed quality inspection
OEE 0%
Overall Equipment Effectiveness
0%
Availability 0%
Performance 0%
Quality 0%
Throughput 0 /hr

📊 Full Breakdown

Metric Value

How the formula works

OEE = Availability × Performance × Quality
  • Run Time = Planned Production Time − Downtime
  • Availability = Run Time ÷ Planned Production Time
  • Performance = (Ideal Cycle Time × Total Units) ÷ Run Time
  • Quality = Good Units ÷ Total Units
  • Industry benchmark: 85%+ OEE is considered world-class, ~60% is typical, below 40% often signals real improvement opportunity